Temporary Precast Concrete Barrier with Pinning Holes on Both Sides (405160-37)

<<Back to Search Results


Transmittal Letter: Final Deliverable-Transmittal Letter

Final Report (Deliverables) Link: 15 ft Barrier Drawings

 

TTI Research Supervisor:
Nauman Sheikh, P.E.
Assistant Research Engineer
Texas Transportation Institute
Texas A&M University System
TAMU 3135
College Station, Texas 77843-3135
(979) 845-8955
[email protected]
Pooled Fund Technical Representative:
Paul B. Fossier, Jr., P.E.
Assistant Bridge Design Administrator
Bridge and Structural Design Section
Louisiana Dept. of Transportation & Development
1201 Capitol Access Road
P.O. Box 94245
Baton Rouge, LA 79084-9245
(225) 379-1323
[email protected]

ABSTRACT:

In this task, TTI developed details of the pinned down temporary concrete barrier with pinning holes on both sides of the barrier. This work was a continuation of previously designed pinned down barrier that had pinning holes on just one side of the barrier (Pooled Fund Project T4541-AB; TTI Project 405160-3). A link to download the set of drawings with design details for pinning holes on both sides of the barrier is presented here.


ELEGIBILITY LETTER LINK:

Not applicable.

VIDEO LINK:

None available.

2017-01-06